1. Conclusion of a contract with the general designer for design and survey work

  2. Performing survey work if necessary

  3. Performing survey work if necessary

  4. Development of an architectural project in accordance with TKP 45-1.02-295-2014 “Construction. Design documentation. Composition and development order ”

  5. Coordination of the project with state bodies and bodies of local government and self-government in the presence of deviations from TNLA and technical conditions

  6. Coordination of the project with the territorial division of architecture and urban planning

  7. Registration of the declaration of conformity of design documentation

  8. obtaining the conclusion of the state examination of the project, if necessary


  9. Approval of an architectural design

  10. Conclusion of a contract for field supervision, if it is not included in the main design contract

  11. Registration of the declaration of conformity of design documentation

  12. Construction and installation works