- Conclusion of a contract with the general designer for design and survey work
- Performing survey work if necessary
- Performing survey work if necessary
- Development of an architectural project in accordance with TKP 45-1.02-295-2014 “Construction. Design documentation. Composition and development order ”
- Coordination of the project with state bodies and bodies of local government and self-government in the presence of deviations from TNLA and technical conditions
- Coordination of the project with the territorial division of architecture and urban planning
- Registration of the declaration of conformity of design documentation
-
obtaining the conclusion of the state examination of the project, if necessary
- Approval of an architectural design
- Conclusion of a contract for field supervision, if it is not included in the main design contract
- Registration of the declaration of conformity of design documentation
- Construction and installation works